Major progress on Kingda Ka's station...
![Image](http://i.imgur.com/rqDAUFl.png)
All the handrails are metal now. Lots of balusters (the vertical parts of handrails) in place. Still lots more to go! This is where the queue enters and splits.
![Image](http://i.imgur.com/IvpBo3v.png)
More balusters and a support for the landing on the other side.
![Image](http://i.imgur.com/uM1GGid.png)
Progress on balusters for the exit stairs.
![Image](http://i.imgur.com/lUYg6Z7.png)
The biggest new addition: Loading operator control panels and safety zones!
![Image](http://i.imgur.com/Hv8cJkF.png)
This is where the most work still needs to be done. The control booth still needs a roof, walls, and especially stairs.
Yes, it's built entirely from supports. It will be integrated into the master park file when it's done, but it still has a ways to go.